Surface Streets
Current Conditions
The Department of Planning, Development, and Neighborhood Conservation (DPDNC) is responsible for planning, prioritizing, and programming improvements to the street system. The Department of Public Works (DPW) is responsible for construction and maintenance of roads and rights-of-way, operation of the street system, including the installation and maintenance of roadway lighting, traffic signals, traffic signs and pavement markings. This system is under the control of the City, with the exception of state-routes, which are controlled by the Georgia Department of Transportation (GDOT). In the city, there are 1,440 miles of surface streets, 450 bridges and viaducts (160 of which are maintained by the City) and 875 traffic signals. Parts of the system have exceeded their expected lifetime.
The City of Atlanta has approximately 40 miles of unpaved streets, which the City intends to pave within the next 15 years. The Department of Planning and Development, in cooperation with DPW, will prepare specific recommendations for paving these streets, including cost estimates and potential funding sources.
The most critical elements in need of replacement or renovation are the bridges, viaducts and traffic signals. The bridges represent the City's most immediate repair, replacement, or reconstruction needs. The state and City continually monitor bridges and viaducts to assess their load capacity and functionality.
Eleven bridges are load-restricted, i.e. heavy trucks and buses are prohibited from crossing them (a list of the load-restricted bridges is on file in the Bureau of Highways and Streets). In addition, the Bankhead Avenue bridge over the CSX rail tracks is closed.
Anticipated Future Conditions
In most areas the existing street system will be able to handle traffic growth through implementation of intersection improvements and turn lane and signalization upgrades. In high-growth areas significant upgrades in system capacity, such as widenings and new street construction will be needed. However, the ability to create new capacity is limited since the Atlanta Region does not meet federal air quality standards.

Map 9.2 Major Roadway System (Popup full image)
Current Policies
- Support the efficient movement of traffic with sensitivity to neighborhood integrity.
- Support pedestrian activity as a preferred mode of transportation in densely developed areas with accommodation for the handicapped.
- Support the pursuit of new funding sources for transportation and pedestrian-system improvements.
- Use traffic signalization improvements and intersection improvements to slow traffic and improve the safety and quality of the pedestrian environment.
- Assure compatibility of freight operations with existing neighborhoods and streets.
- Support bicycling as a preferred mode of nonpolluting transportation by constructing bicycle facilities throughout the City.
- Promote the paving of all city streets to control dust pollution and reduce city maintenance costs.
- Update and Implement a citywide pedestrian plan and program.
- Promote and plan for greater street connectivity in major travel corridors.
Current Programs and Projects
Programs and projects can be categorized into four areas: maintenance, capacity and safety improvements, alternative modes of travel, and signalization.
Maintenance includes resurfacing, curb and sidewalk repair, and bridge/viaduct renovation or replacement. Capacity and safety improvements include intersection improvements, addition of turn lanes and comprehensive widening projects. Alternative modes of travel include pedestrian and bicycle facilities such as new sidewalks, greenway trails, and bike lanes. Signalization includes installing new signals, expanding the computer-controlled signal system, and modernizing signal equipment.
Maintenance
Major initiatives in maintenance activities are related to assuring the continued service of the City's bridges and viaducts. These structures must be able to carry vehicular weights consistent with the street's function. Evaluation of all bridges and viaducts is continuing by DPW engineering staff, with the goal of establishing a prioritized program of renovation and replacement. Structures already identified for need of immediate attention are the Spring Street Viaduct, and the Peachtree Street Viaduct.
Capacity And Safety
Capacity and safety improvement projects include widening Campbellton Road, Lenox Road, and Roxboro Road; and improving the interchanges at Greenbriar Parkway, Campbellton Road and Langford Parkway.
Modification of intersections is a high return on investment means of improving traffic flow. Ten intersection improvement projects are included in the listing of projects at the end of this section. Also, GDOT plans include improvements to various intersections along Northside Drive from I-75 to I-20. Preliminary engineering and design are required in order to identify changes to the intersection geometries. Other locations will be considered during this process of identifying low-cost intersection improvements.
Three railroad overpasses will be replaced as part of roadway widening projects. These are the CSX Railroad overpass on Bankhead Highway, the CSX Railroad overpass on Northside Drive and the Norfolk-Southern Railroad overpass on Northside Drive.
Alternative Modes Of Transportation
The City is committed to implementing strategies for reducing automobile source emissions ozone-causing pollutants. One strategy is to construct pedestrian and bicycle facilities that offer citizens and visitors alternative means of travel. Transit-oriented sidewalks that have the greatest potential for reducing dependence on Single Occupancy Vehicles (SOVs). The City is constructing a network of multi-use greenway trails and on-street bikeways to reduce dependence on the automobile.
Signalization
The DPW has initiated a program to upgrade the existing signal-control equipment and to replace the central computer. To that end, a project that provides funds for the design and installation of the Atlanta Transportation Management System (ATMS) is underway. The Inter-modal Surface Transportation Efficiency Act (ISTEA) and other funding have been a major source of support for this project. Now under the Transportation Equity Act for the 21st century (TEA-21), the City is receiving portions of a $58 million grant to complete this project.
Intersections
Project List 9-2: 2004 CDP Transportation Current Programs and Projects - Intersections
|
Transportation Intersections |
Description |
Initiation Year |
Completion Year |
COST x 1,000 |
Funding Source |
Responsible Party |
CIP # |
NPU |
CD |
||
|
1 |
5 |
15 |
|||||||||
|
1 |
Bolton Rd at Marietta |
15 |
2016 |
350 |
Annual Bond Fund / D.I. F, Federal |
DPW |
SB-005 |
D,G |
8,9 |
||
|
2 |
Buford Hwy at Sidney Marcus Blvd |
5 |
2004 |
2000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
n. i. |
B |
7 |
||
|
3 |
Butler St./Auburn Ave. Intersection Improvements |
15 |
2016 |
1500 |
GDOT, Federal |
DPW |
n. i. |
M |
2 |
||
|
4 |
Channelization and Islands |
1 |
5 |
15 |
1999 |
200 |
Annual Bond Fund / D.I. F, Federal |
DPW |
TE-007 |
all |
all |
|
5 |
Cheshire Bridge Rd at Lindbergh Dr. |
5 |
2006 |
2500 |
Annual Bond Fund / D.I. F, Federal |
DPW |
SB-074 |
F |
6 |
||
|
6 |
McDaniel St at So RR |
15 |
2016 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
n. i. |
V |
2,4 |
||
|
7 |
Memorial Dr at Boulevard |
5 |
2006 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
n. i. |
N,W |
1,5 |
||
|
8 |
Memorial Dr at Moreland Ave. |
1 |
2004 |
500 |
Annual Bond Fund / D.I. F, Federal |
DPW |
n. i. |
O,W |
5 |
||
|
9 |
Memorial ar Candler Rd. |
1 |
2004 |
500 |
Annual Bond Fund / D.I. F, Federal |
DPW |
n. i. |
O,W |
5 |
||
|
10 |
MLK Jr. Dr at Ashby |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
SB-222 |
K,L,T |
3,4 |
||
|
11 |
Moreland Avenue at Glenwood Avenue |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
SB-232 |
W |
1,5 |
||
|
12 |
Moreland Avenue at Memorial Dr & Arkwright Place |
5 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
SB-231 |
N,O |
5 |
||
|
13 |
Northside Dr at 10th, 14th, McDaniel, Fair, Mitchell, Simpson, MLK, North and Bankhead Hwy |
5 |
15 |
2019 |
10000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
SB-224 |
E,M |
2,3 |
|
|
14 |
Peachtree Rd at Lenox Pkwy |
5 |
2004 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
n. i. |
B |
7 |
||
|
15 |
Peachtree Rd at Tower Place Drive |
5 |
2009 |
50 |
Annual Bond Fund / D.I F, Federal |
DPW |
n. i. |
B |
7 |
||
|
16 |
Southwest Atlanta Plan – I-20 Ramp Improvements @ MLK, Jr. Drive |
5 |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
N/A |
I |
10 |
|
|
17 |
Southwest Atlanta Plan – Abernathy & MLK, Jr. Drive Improvements |
5 |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
N/A |
I |
10 |
|
|
19 |
Southwest Atlanta Plan – Fairburn & Benjamin E. Mays Drive Improvements |
5 |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
N/A |
H |
10 |
|
|
20 |
Southwest Atlanta Plan – Cascade Road & Benjamin E. Mays Drive |
5 |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
N/A |
I |
10 |
|
|
21 |
Southwest Atlanta Plan – Mt. Gilead/Campbellton Road Improvements |
5 |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
N/A |
R |
11 |
|
|
22 |
Southwest Atlanta Plan – Fairburn Road & Campbellton |
1 |
5 |
15 |
2019 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
N/A |
P |
11 |
|
-deleted- |
|||||||||||
|
24 |
Southwest Atlanta Plan – Railroad Intersection Improvements |
1 |
5 |
2009 |
1000 |
Annual Bond Fund / D.I. F, Federal |
DPW |
N/A |
H, I, P, R |
10, 11 |
|
|
25 |
Metropolitan Pkwy (Stewart Avenue) intersection improvements |
5 |
15 |
2019 |
7500 |
Annual Bond Fund / D.I. F, Federal |
DPW |
n.i. |
X |
12 |
|
|
26 |
14th St. fr. Techwood Dr. to West Peachtree |
5 |
2009 |
2000 |
Annual Bond Fund / Dev. Impact fees, Federal |
DPW |
n. i. |
E |
7 |
||
|
27 |
Briarcliff Rd. at Ponce de Leon Ave. |
5 |
2009 |
2500 |
Annual Bond Fund / Dev. Impact fees, Federal |
DPW |
n. i. |
F |
6 |
||
|
28 |
Fairburn Rd @ Ben E. Mays Dr. |
5 |
2009 |
1000 |
Annual Bond Fund / Dev. Impact fees, Federal |
DPW |
n. i. |
H |
10 |
||
|
29 |
Hutchens Rd. @ School Rd./Jonesboro Rd. |
5 |
2009 |
500 |
Annual Bond Fund / Dev. Impact fees, Federal |
DPW |
n. i. |
Z |
12 |
||
|
30 |
Jonesboro Rd. fr. Macedonia Rd. to Hutchens and School Rd. |
5 |
2009 |
500 |
Annual Bond Fund / Dev. Impact fees, Federal |
DPW |
n. i. |
Z |
12 |
||
|
31 |
McDonough/University/Ridge/Hank Aaron Dr. |
5 |
2009 |
1500 |
Annual Bond Fund / Dev. Impact fees, Federal |
DPW |
n. i. |
V, Y |
1,2,4 |
||
|
32 |
Piedmont Rd. @Sidney Marcus BLVD., Morosgo Dr., Lindbergh Dr., and Garson Rd. |
5 |
2009 |
7500 |
Dev. Impact Fees / TEA-21, Federal |
DPW. |
B |
7 |
|||
|
33 |
Virginia Ave. @ Highland Ave. |
5 |
2009 |
500 |
Annual Bond Fund / Dev. Impact fees, Federal |
DPW. |
F |
6 |
|||
New Street Construction
Project List 9-3: 2004 CDP Transportation Current Programs and Projects – New Street Construction
|
Transportation New Street Construction |
Description |
Initiation Year |
Completion Year |
COST x 1,000 |
Funding Source |
Responsible Party |
CIP # |
NPU |
CD |
||
|
1 |
5 |
15 |
|||||||||
|
1 |
Barge Rd/ Greenbriar Pkwy Connector |
|
|
15 |
2004 |
800 |
GDOT, Federal |
|
SB-260 |
R |
11 |
|
2 |
Beatie Street Extension to Calhoun |
|
|
15 |
2019 |
500 |
GDOT, Federal |
DPW |
n. i. |
X |
12 |
|
3 |
Culpepper St Extension to Ellsworth |
|
|
15 |
2019 |
700 |
GDOT, Federal |
DPW |
n. i. |
D |
8 |
|
4 |
Glenwood-Land Port Connector from the Glenwood-Memorial Drive Connector to Wylie St |
|
|
15 |
2019 |
1000 |
GDOT, Federal |
DPW |
SB-218 |
N,W |
5 |
|
5 |
James Avenue from Old Hightower Road to Fifth Street |
|
|
15 |
TBD |
TBD |
GDOT, Federal |
DPW |
|
G |
9 |
|
6 |
Mechanicsville Truck Route |
|
5 |
|
2009 |
1327 |
GDOT, Federal |
DPW |
n. i. |
V |
2,4 |
|
7 |
Stone-Hogan Extension to North Desert Drive |
|
|
15 |
2019 |
1500 |
GDOT, Federal |
DPW |
SB-254 |
R |
11 |
Project List 9-4: 2004 CDP Transportation Deleted Programs and Projects – New Street Construction
|
Transportation New Street Construction |
Description |
|
|
None |
|
|
|
Street Reconstruction
Project List 9-5: 2004 CDP Transportation Current Programs and Projects – Street Reconstruction
|
Transportation Street Construction |
Description |
Initiation Year |
Completion Year |
COST x 1,000 |
Funding Source |
Responsible Party |
CIP # |
NPU |
CD |
||
|
1 |
5 |
15 |
|||||||||
|
1 |
Airline Street |
|
5 |
|
2004 |
|
General Fund |
DPW |
n.i. |
M |
2 |
|
2 |
Mitchell St from Spring St to Capitol Ave |
|
|
15 |
2019 |
1600 |
General Fund |
DPW |
SB167 |
M |
2 |
|
3 |
Piedmont Avenue from Decatur to Ralph McGill Blvd |
1 |
|
|
1999 |
2300 |
General Fund |
DPW |
SB181 |
M |
2 |
|
4 |
Southwest Atlanta Plan – Peyton Road Horizontal Curve |
|
5 |
15 |
2009 |
|
|
DPW |
N/A |
I |
10 |
|
5 |
Southwest Atlanta Plan – MLK, Jr. Drive Realignment |
|
|
15 |
2019 |
|
|
DPW |
N/A |
I |
10 |
|
6 |
Southwest Atlanta Plan – Greenbriar mall Access Improvements |
|
5 |
15 |
2019 |
|
|
DPW |
N/A |
P, R |
11 |
|
7 |
Southwest Atlanta Plan – I-285 Noise Abatement Program |
1 |
5 |
|
2019 |
|
|
DPW |
N/A |
H, I, P, R |
10, 11 |
|
8 |
Walton Street from Marietta to Peachtree |
|
|
15 |
2019 |
1100 |
General Fund |
DPW |
SB173 |
M |
2 |
Street Widenings and Upgrades
Project List 9-6: 2004 CDP Transportation Current Programs and Projects – Street Widenings and Upgrades
|
Transportation Street Widenings and Upgrades |
Description |
Initiation Year |
Completion Year |
COST x 1,000 |
Funding Source |
Responsible Party |
CIP # |
NPU |
CD |
||
|
1 |
5 |
15 |
|||||||||
|
1 |
Alexander, Jones & Simpson Streets from W Peachtree St to Northside Drive (a.k.a. McGill Extension) |
1 |
|
|
2009 |
4000 |
Bond Fund, Federal |
DPW |
SB33 |
M |
2 |
|
2 |
Bankhead Hwy from Gary to Law; and from Harwell Rd to Holmes Drive |
|
5 |
|
2009 |
900 |
Bond Fund, Federal |
DPW |
SB49 |
G,H,I,K |
9 |
|
3 |
Bolton Rd from Fulton Industrial to Marietta |
|
|
15 |
2019 |
4000 |
Bond Fund, Federal |
DPW |
n.i. |
D,G |
8,9 |
|
4 |
Campbellton Rd from Barge Rd to City Limits |
|
|
15 |
2019 |
5500 |
Bond Fund, Federal |
DPW |
SB090 |
P |
11 |
|
5 |
Campbellton Rd Segments :; Phase III- Harbin to Willis Mill; Phase IV- Timothy to Ft McPherson; Phase V- Ft McPherson Gate to Lee Street |
|
5 |
15 |
2019 |
12004 |
Bond Fund, Federal |
DPW |
SB06 |
P,R |
11 |
|
6 |
DeKalb Avenue from Jackson St to Moreland Avenue |
|
|
15 |
2019 |
18000 |
Bond Fund, Federal |
DPW |
SB244 |
M,N |
2,5 |
|
7 |
Eighth St from Williams St to Juniper |
|
|
15 |
2019 |
1000 |
Bond Fund, Federal |
DPW |
SB242 |
E |
7 |
|
8 |
Eleventh St from W Peachtree St to Piedmont Ave |
|
|
15 |
2019 |
3000 |
Bond Fund, Federal |
DPW |
SB245 |
E |
7 |
|
9 |
Fairburn Rd from Benjamin E. Mays Dr. to City Limits |
|
5 |
|
2009 |
5100 |
Bond Fund, Federal |
DPW |
SB418 |
H |
10 |
|
10 |
Fifth Street from Williams St to Peachtree St |
|
|
15 |
2019 |
1925 |
Bond Fund, Federal, Private |
DPW |
SB409 |
E |
7 |
|
11 |
Fulton Industrial Blvd from North Aviation Circle to Bankhead Hwy |
|
5 |
|
2009 |
7560 |
Bond Fund, Federal |
DPW |
SB60 |
H |
9 |
|
12 |
Hilliard St from Chamberlin to Auburn Avenue |
|
|
15 |
2019 |
127 |
Bond Fund, Federal |
DPW |
n.i. |
M |
2 |
|
13 |
HE Holmes Drive from I-20 to Bankhead Hwy |
|
5 |
|
2004 |
5000 |
Bond Fund, Federal |
DPW |
n.i. |
G,H,J |
3,9 |
|
14 |
Howell Mill from Marietta St to Collier Rd |
|
5 |
15 |
2019 |
300 |
Bond Fund, Federal |
DPW |
SB212 |
D |
8 |
|
15 |
Huff Rd from Howell Mill to Marietta Blvd |
|
|
15 |
2019 |
500 |
Bond Fund, Federal |
DPW |
SB25 |
D |
8 |
|
16 |
Lenox Rd from Canterbury Rd to Ferncliff Rd |
|
5 |
|
2009 |
5100 |
Bond Fund, Federal |
DPW |
SB152 |
B |
6 |
|
17 |
Marietta Blvd from Bolton Rd to City Limits |
|
5 |
|
2009 |
1500 |
Bond Fund, Federal |
DPW |
SB102 |
C,D |
8 |
|
18 |
Memorial Drive from Pearl to Whitefoord |
|
|
15 |
2019 |
10000 |
Bond Fund, Federal |
DPW |
SB243 |
N,O |
5 |
|
19 |
MLK Jr. Dr. from Bolton Rd to West Lake Avenue |
|
|
15 |
2019 |
3000 |
Bond Fund, Federal |
DPW |
SB410 |
I |
|
|
20 |
MLK Jr. Dr. improvements: Contract 2) widen from Barfield to Holmes Drive and Fairburn Road; 3) improve intersection at Lynhurst |
|
5 |
15 |
2004 |
1000 |
Bond Fund, Federal |
DPW |
n.i. |
H |
9 |
|
21 |
Northside Dr. from I-20 to I-75 |
|
5 |
|
2009 |
36670 |
Bond Fund, Federal |
DPW |
n.i. |
D,E |
8 |
|
22 |
Pine St from Peachtree St to Piedmont Ave |
|
|
15 |
2019 |
1000 |
Bond Fund, Federal |
DPW |
SB082 |
M |
2 |
|
23 |
|
|
|
|
|
|
|
|
|
|
|
|
24 |
Seventh St from Juniper to W Peachtree |
|
|
15 |
2019 |
3000 |
Bond Fund, Federal |
DPW |
SB248 |
E |
7 |
|
25 |
Southside Industrial Pkwy from Crown to Gilbert Rd |
|
5 |
|
2009 |
1500 |
Bond Fund, Federal |
DPW |
SB092 |
Z |
12 |
|
26 |
Southwest Atlanta Plan – MLK, Jr. Drive Streetscape |
1 |
5 |
15 |
2019 |
|
Bond Fund, Federal |
DPW |
N/A |
H, I |
10 |
|
27 |
Southwest Atlanta Plan – Fairburn Road – Bolton to Cascade |
|
5 |
15 |
2019 |
|
Bond Fund, Federal |
DPW |
N/A |
H, I |
10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
29 |
Thirteenth St from Juniper to W Peachtree |
|
|
15 |
2019 |
1000 |
Bond Fund, Federal |
DPW |
SB246 |
E |
7 |
|
30 |
University Avenue |
|
5 |
|
2009 |
4000 |
Bond Fund/Federal |
DPW |
|
|
|
Upgrade Existing Bridges and Viaducts
Project List 9-7: 2004 CDP Transportation Current Programs and Projects – Upgrade Existing Bridges and Viaducts
|
Transportation Upgrade Existing Bridges and Viaducts |
Description |
Initiation Year |
Completion Year |
COST x 1,000 |
Funding Source |
Responsible Party |
CIP # |
NPU |
CD |
||
|
1 |
5 |
15 |
|||||||||
|
1 |
17th Street Bridge |
1 |
5 |
|
2009 |
70,000 |
State, Federal |
DPW |
n. i. |
E |
8 |
|
2 |
Bankhead Hwy at So RR |
|
5 |
|
2009 |
1600 |
State, Federal |
DPW |
SB186 |
E, L |
8 |
|
3 |
Bohler Rd at Peachtree Creek |
|
5 |
|
2009 |
2130 |
Bond Fund, Federal |
DPW |
SB65 |
C |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
Browns Mill Road Bridge @ Empire Creek |
|
5 |
15 |
2019 |
1200 |
Bond Fund, Federal |
DPW |
n.i. |
Z |
12 |
|
6 |
Butler Street bridge recst |
|
5 |
|
2009 |
300 |
State, Federal |
DPW |
SB286 |
M |
2 |
|
7 |
Central Avenue bridge over CSX RR |
|
5 |
|
2009 |
300 |
Bond Fund, Federal |
DPW |
SB281 |
M |
2 |
|
8 |
Childress Road Bridge @ South Utoy Creek |
|
5 |
15 |
2019 |
1000 |
Bond Fund, Federal |
DPW |
n.i. |
I, R |
11 |
|
9 |
CSX RR bridge over Northside Drive |
|
5 |
|
2009 |
6480 |
Bond Fund, Federal |
DPW |
n.i. |
D |
9 |
|
10 |
CSX RR bridge over Piedmont Avenue |
|
5 |
|
2009 |
300 |
State, Federal |
DPW |
SB284 |
M |
2 |
|
11 |
Dodson Drive Bridge @ South Utoy Creek |
|
5 |
15 |
2019 |
1200 |
Bond Fund |
DPW |
n.i. |
R |
11 |
|
12 |
Fairburn Rd bridge north of Hogan Rd over CSX RR |
1 |
|
|
2009 |
510 |
Bond Fund, Federal |
DPW |
SB405 |
P |
11 |
|
13 |
Fairburn Rd bridge south of Stone Rd over CSX RR |
1 |
|
|
2009 |
680 |
State, Federal |
DPW |
SB403 |
P |
11 |
|
14 |
Harbin road Bridge @ South Utoy Creek |
|
5 |
15 |
2019 |
1200 |
Bond Fund |
DPW |
n.i. |
I, R |
11 |
|
15 |
International Blvd bridge over CSX RR |
1 |
|
|
2009 |
1600 |
State, Federal |
DPW |
SB283 |
M |
2 |
|
16 |
Johnson Rd bridge at Proctor Creek |
|
|
15 |
2019 |
1700 |
Bond Fund |
DPW |
SB67 |
G,J |
9 |
|
17 |
Lenox Road Bridge @ South Fork Peachtree Creek |
|
5 |
15 |
2019 |
900 |
Bond Fund |
DPW |
n.i. |
F |
6 |
|
18 |
MLK Jr. Dr. bridge from Forsyth St to Spring St |
1 |
5 |
|
2009 |
3000 |
Bond Fund, Federal |
DPW |
n.i. |
M |
2 |
|
19 |
Moores Mill Rd at Peachtree Creek |
|
5 |
|
2009 |
2400 |
Bond Fund |
DPW |
SB64 |
A,C |
8 |
|
20 |
Norfolk So RR bridge over Northside Dr |
|
5 |
|
2009 |
6480 |
Bond Fund, Federal |
DPW |
n.i. |
D,E |
9 |
|
21 |
Northside Dr at Peachtree Creek |
|
|
15 |
2019 |
5400 |
Bond Fund, Federal |
DPW |
SB66 |
C |
8 |
|
22 |
Peachtree St bridge at Wall St |
|
5 |
|
2009 |
0 |
State, Federal |
DPW |
n.i. |
M |
2 |
|
23 |
Pryor St viaduct over CSX RR |
|
5 |
|
2004 |
600 |
State, Federal |
DPW |
SB287 |
M |
2 |
|
24 |
Ridegewood Road Bridge @ Nancy Creek |
|
5 |
15 |
2019 |
1200 |
Bond Fund |
DPW |
n.i. |
A, C |
8, 9 |
|
25 |
Sring St. (Techwood Dr) viaduct over CSX RR |
|
5 |
|
2008 |
500 |
State, Federal |
DPW |
SB285 |
M |
2 |
|
26 |
Wieuca Rd Bridge @ Nancy Creek |
|
5 |
15 |
2019 |
850 |
Bond Fund |
DPW |
n.i. |
B |
7 |
Upgrade Existing Facilities
Project List 9-8: 2004 CDP Transportation Current Programs and Projects – Upgrade Existing Facilities
|
Trans. Upgrade Existing Facilities |
Description |
Initiation Year |
Completion Year |
COST x 1,000 |
Funding Source |
Responsible Party |
CIP # |
NPU |
CD |
||
|
1 |
5 |
15 |
|||||||||
|
1 |
Atlanta Multi-modal Passenger Terminal |
1 |
5 |
15 |
2019 |
169000 |
Federal Funds |
DPW |
n.i. |
M |
2 |
|
2 |
CDBG Sidewalk Assessment |
1 |
|
|
1999 |
200 |
CDBG |
DPW |
SB159 |
all |
all |
|
3 |
MLK/Ashby Street |
1 |
5 |
|
2004 |
3770 |
General Fund |
DPW |
n.i. |
T |
4 |
|
4 |
Neighborhood Sidewalk Improvements |
1 |
5 |
|
2004 |
500 |
General Fund |
DPW |
SB205 |
all |
all |
|
5 |
Neighborhood Traffic Management |
|
5 |
|
2004. |
40 |
General Fund |
DPW |
TE058 |
all |
all |
|
6 |
Northside Drive Signalization |
1 |
|
|
2005 |
6640 |
General Fund |
DPW |
n.i. |
D,E |
2,3 |
|
7 |
Overhead Street Name Signs |
1 |
5 |
|
2004. |
40 |
General Fund |
DPW |
TE061 |
all |
all |
|
8 |
Peachtree Street |
1 |
5 |
|
2004 |
5500 |
General Fund |
DPW |
n.i. |
E,M |
2,7 |
|
9 |
Traffic Calming Measures/Speed Hump Installations |
1 |
5 |
|
2004 |
4300 |
General Fund |
DPW |
n.i. |
all |
all |
|
10 |
Street Light Modernization |
1 |
5 |
15 |
2019 |
5700 |
General Fund |
DPW |
TE 106 |
all |
all |
|
11 |
Summerhill Neighborhood Streets – Phase II |
1 |
5 |
|
2004 |
1900 |
General Fund |
DPW |
n.i. |
V |
2 |
|
12 |
Traffic Operations Improvements |
|
5 |
|
2004. |
600 |
General Fund |
DPW |
TE056 |
all |
all |
|
13 |
Traffic Signal Modernization |
1 |
5 |
|
2004 |
10000 |
General Fund |
DPW |
TE004 |
all |
all |
|
14 |
Unpaved Streets - NE |
1 |
5 |
|
2004 |
330 |
General Fund |
DPW |
n.i. |
E, F, B |
2, 6, 7 |
|
15 |
Unpaved Streets - NW |
1 |
5 |
|
2004 |
2163 |
General Fund |
DPW |
n.i. |
A, C, D, G, J, K, L |
3, 8, 9 |
|
16 |
Unpaved Streets - SE |
1 |
5 |
|
2004 |
1343 |
General Fund |
DPW |
n.i. |
O, W, Y, Z |
1, 2, 5, 12 |
|
17 |
Unpaved Streets - SW |
1 |
5 |
|
2004 |
15021 |
General Fund |
DPW |
n.i. |
H, I, P, R, S, T,V,X |
4, 10, 11, 12 |
Support Facilities
Project List 9-9: 2004 CDP Transportation Current Programs and Projects – Support Facilities
|
Transportation Support Facilities |
Description |
Initiation Year |
Completion Year |
COST x 1,000 |
Funding Source |
Responsible Party |
CIP # |
NPU |
CD |
||
|
1 |
5 |
15 |
|||||||||
|
1 |
ComCare Housing Site Improvements |
|
5 |
|
2004. |
14 |
General Fund |
DPW |
n.i. |
|
|
|
2 |
Hill Street Concrete Plant |
|
5 |
|
2004 |
450 |
General Fund |
DPW |
SB194 |
W |
1 |
|
3 |
Hill Street Maintenance Facility |
|
5 |
|
2004 |
600 |
General Fund |
DPW |
SB193 |
W |
1 |
|
4 |
Street and Sidewalk Assessment Program |
1 |
5 |
|
2004 |
100 |
General Fund |
DPW |
n.i. |
|
|
|
5 |
Truck & Equipment Wash Facility |
|
5 |
|
2004 |
300 |
General Fund |
DPW |
SB211 |
X |
12 |