Bicycle Facilities

Current Conditions

Currently, less than one percent of Atlanta’s residents commute to work or school by bike.  The City and its residents are, however, making an effort to increase bicycle awareness and improve cycling conditions.  The promotion of cycling as a viable mode of transportation is especially important due to regional air quality considerations.  By providing safe and convenient bicycle facilities, the City hopes to increase bicycle ridership, thereby reducing dependence on motorized travel.  The City has made much progress in recent years toward providing bicycle facilities for the public.  Three formal programs exist.  They are the City of Atlanta Greenway Trail Corridor Plan, the Atlanta Commuter On-Street Bike Plan, and the City of Atlanta Bicycle Parking Program.

Greenway Trail Corridor Plan

The City of Atlanta Greenway Trail Corridor Plan was developed through a Citywide, volunteer-sponsored, public participation process in 1991-92.  The City and the PATH Foundation in October 1992 published the final Plan.  In 1993, the Greenway Trail Corridor Plan became part of the larger Atlanta Parks, Open Space, and Greenways Plan.  Since that time, the City of Atlanta has worked jointly with the PATH Foundation to implement the Greenway Trail Corridor Plan.  Five trails have been completed and six are under design or construction.   Greenway trails are to be used for non-motorized forms of transit, such as walking, jogging, cycling, and skating.  They will provide transportation and recreational opportunities as well as safe, easy access to schools, workplaces, major activity centers, parks, and historic and cultural facilities for all City residents.

Atlanta Commuter On-street Bike Plan

The Atlanta Commuter On-Street Bike Plan seeks to develop a safe transportation network geared toward moving commuter cyclists through the City.  The Atlanta Commuter On-Street Bike Plan was developed in 1995 by the Bureau of Planning and the Mayor’s Bicycle Planning Committee, which included representatives from the Department of Public Works, the Georgia Department of Transportation, the Atlanta Regional Commission, the PATH Foundation, neighborhood planning units, and local bicycle organizations.  The Commuter On-Street Bike Plan calls for designated bicycle routes including bike lanes, bike shoulders, wide curb lanes, and shared travel lanes to be installed on existing streets.  The Plan also identifies policies, implementation strategies, design standards, and other related bicycle information.   In 2002, the on-street bike plan received an update to reflect completed routes and changes to planned routes. Over the next 10 years, over 300 miles of designated bike routes are to be installed in the City.

Bicycle Parking Program

The City of Atlanta Bicycle Parking Program was initiated in 1994 when City Council President Marvin Arrington and Councilmember Mary Davis organized the City Council Bicycle Parking Task Force to examine bicycle parking issues and needs throughout the City.  The Committee worked closely with the Mayor’s Bicycle Planning Committee and the Corporation for Olympic Development in Atlanta to install almost 200 bike racks in the City prior to the Olympic Games.  Additional bicycle racks have been donated to the City and will be installed in locations Citywide.  The Department of Planning and Development is prioritizing suggested locations submitted by neighborhood planning units, cycling organizations, the Atlanta Bicycle Planning Committee, and concerned citizens.

Atlanta Bicycle Planning Committee

On December 2, 1996 the membership of the Mayor’s Bicycle Planning Committee and the City Council Bicycle Parking Task Force were officially merged to form the Atlanta Bicycle Planning Committee.  Members include representatives from City departments, the Atlanta Regional Commission, the Georgia Department of Transportation, MARTA, the PATH Foundation, neighborhood planning units, and area bicycle organizations.  The Committee works with the City to help implement the City’s bicycle programs and guide bicycle policy.  Committee meetings are open to the public and all participants are welcome.


Anticipated Future Conditions

The City will continue to work with the PATH Foundation to construct the City’s greenway trail system.  Eventually, these handicapped accessible, multi-use trails will link the City’s neighborhoods and parks with each other, with commercial districts, and with cultural and historic resources.  It will be possible for a resident from Southwest Atlanta to travel by trail from Greenbriar Mall to Fernbank Museum or to the Chattahoochee River National Recreation Area.  It is anticipated that the greenway trail system will be used by 50 percent of the surrounding population for transportation and recreational uses.

The City will continue to work with the Atlanta Bicycle Planning Committee to implement the Commuter On-Street Bike Plan.  New routes will be designed each year.  Major routes, designated as one- and five-year projects in the Commuter On-Street Bike Plan, will be constructed primarily as bike lanes and may require road widening.  Other bicycle routes may be constructed as part of scheduled road improvement projects.

The City and the Atlanta Bicycle Planning Committee will work to develop policies regarding bicycle parking.  Efforts will be made to increase the provision of bicycle parking facilities in new commercial and residential developments.  The City will also increase bicycle-parking facilities in public areas and investigate programs that would encourage private property owners to improve bicycle-parking facilities in existing private developments. 

Current Policies

  1. Increase bicycle ridership as a viable mode of transportation by providing a network of on-street bikeways that is accessible to all neighborhoods and serves residents, commuters and visitors.
  2. Incorporate bicycle facilities into the City’s transportation planning process.
  3. Promote bicycle safety, education, and awareness.
  4. Provide efficient and effective maintenance on all on-street bike facilities, thereby providing optimal commuting and recreational opportunities.
  5. Promote the provision of pedestrian and bicycle transportation facilities in new commercial and residential developments.
  6. Develop a system of multi-use recreational trails within the open space and greenways system, for use by all ages.

Current Programs and Projects

Several new greenway trails are under design or construction including sections of the Chattahoochee Trail and Fort Peachtree Trail, the Arts District Trail from Downtown to Atlanta Memorial Park, the Southtowne Trail, Freedom Trail, and the West End Trail.

Work has begun on the five-year priority bike routes listed in the Commuter On-Street Bike Plan.  These include North Highland Avenue, Cascade Road, Berne Street, Wesley Road, James Jackson Parkway, Jonesboro Road, Browns Mill Road, and Flat Shoals Avenue.  These projects are inter-jurisdictional routes that link major activity centers, MARTA transit stations, and greenway trails.  They are important to the success of the on-street network since they provide the basic trunk system and connections to all other bike routes.  They will be constructed primarily as bike lanes, which may require widening some affected streets.  Other on-street routes may be implemented in conjunction with scheduled road improvement projects such as Lenox Road and Campbellton Road.

The City is in the process of installing additional bicycle racks Citywide.  Suggestions for locations have been solicited from neighborhood planning units, cycling organizations, and the Atlanta Bicycle Planning Committee.  Criteria have been developed to determine final locations.

Project List 9-12: 2004 CDP Transportation Current Programs and Projects – Bicycle Facilities

Transportation Bicycle Facilities

Description

Initiation Year

Completion Year

COST
x 1,000

Funding Source

Responsible Party

CIP #

NPU

CD

1

5

15

1

Ansley Park from Piedmont Park to Lenox Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

E

6,7

2

Benjamin E. Mays Drive from Fairburn to Cascade



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

H,I,S

6,7

3

Berne Street from Grant Park to City Limits

1



2004

8

Gen. Fund/ Federal

DPW

n. i.

W

1, 5

4

Bike Racks Citywide

1



2004

113

Gen. Fund/ Federal

DPW

n. i.

all

all

5

Bolton Road from Jackson Parkway to MLK Jr. Drive



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

D, G, H

9, 10

6

Bolton Road from Jackson PKWY to Marietta Boulevard


5


2009

9

Gen. Fund/ Federal

DPW

n. i.

D

9

7

Boulder Park from City Limits to MLK Jr. Drive



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

H

10

8

Boulevard Drive from City Limits to Grant Park



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

O,W

1,5

9

Browns Mill Road - Marietta Street to Southside Pk


5


2009

20

Gen. Fund/ Federal

DPW

n. i.

V, Y, Z

1, 2, 12

10

Campbellton Road from City Limits to Sandtown Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

P,R,S

11,12

11

Cascade Road - City Limits to West End MARTA

1



2004

17

Gen. Fund/ Federal

DPW

n. i.

I, S

4, 11

12

Chastain Park- West Wesley Road from Chastain Park to West Wesley Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

A,C

8

13

Chastain Park-Moores Mill Road


5


2009

13

Gen. Fund/ Federal

DPW

n. i.

A, C

8

14

Claire Drive from Ridge Ave to Browns Mill Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

Y,Z

4,12

15

Cleveland Ave from City Limits to Jonesboro Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

X,Z

12

16

Clifton Road from Clifton Terrace to City Limits



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

N

6

17

Collier Drive from Gordon Road to J. P. Brawley Drive

1



2004

0

Gen. Fund/ Federal

DPW

n. i.

I

10

18

Colony Parkway from Greenbriar Mall to City Limits


5


2009

9

Gen. Fund/ Federal

DPW

n. i.

R, P

11

19

County Line Road from City Limits to Butner Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

P

11

20

Custer Avenue from McDonough Blvd to Woodland Avenue



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

W

1

21

Defoors Ferry Road from Moores Mill Road to Howell Mill Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

C, D

9

22

Delowe Drive from Cascade Road to City Limits



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

R

11

23

Downtown Loop

1



2004

307

Gen. Fund/ Federal

DPW

n. i.

E, M

2, 6

24

East Confederate Avenue from Grant Park to Woodland Avenue



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

W

1

25

Edgewood Avenue/ McLendon Avenue form Five Points MARTA station to City Limits



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

M,N,O

2,5,6

26

Fairburn Road from Bolton Road to City Limits



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

H,P

10,11

27

Forest Park Road - McDonough Blvd to City Limits


5


2009

14

Gen. Fund/ Federal

DPW

n. i.

Z

1, 12

28

Fulton Street and Glenwood Avenue from RDA Blvd to Oakview Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

V,W

1,2,4

29

Grove Park from Johnson Road to RDA Blvd



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

J,K

3,4,9

30

Hapeville Road from Macon Drive to Browns Mill Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

Z

12

31

Hill Street from Memorial Drive to Lakewood Way



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

W

2

32

Hilliard/ Cherokee from John Wesley Dobbs to Grant Park



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

W

1,2,5

33

Hollywood Road from Bolton Road to Marietta Street



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

D, G, J

3,9

34

Howell Mill Road - Moores Mill Road to Tech Parkway


5


2009

605

Gen. Fund/ Federal

DPW

n. i.

C, D, E, M

2, 8

35

Irwin Street from Five Points to Euclid Avenue



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

M,N

2

36

James Jackson PKWY – City Limits to Hightower MARTA

1



2004

401

Gen. Fund/ Federal

DPW

n. i.

D, G, I, J

3, 9, 10

37

James P. Brawley Drive from Greensferry Street to Marietta Street



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

L,T

3,4

38

John A. White Park – Cleveland Ave. from Casacde Rd. to Cleveland Ave.


5


2009

20

Gen. Fund/ Federal

DPW

n. i.

S, X, Y, Z

4, 11, 12

39

Johnson Road from Hollywood to Peachtree Street



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

C,D

7,8,9

40

Johnson Road/ Briarcliff from E. Rock Springs Road to City Limits



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

F

6

41

Jonesboro Road from Ridge Avenue to City Limits



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

Y,Z

1,12

42

Kimberly Road-Butner Road from Cascade to Tell Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

P

11

43

Lee Street/ Venetian Drive from Greensferry Road to Cascade Rd.



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

S,T

4

44

Lee/Whitehall Street - Memorial Dr. to City Limits


5


2009

12

Gen. Fund/ Federal

DPW

n. i.

S, T, V, X

2, 4, 12

45

Lenox Road - Peachtree Road to Virginia Avenue

1



2004

308

Gen. Fund/ Federal

DPW

n. i.

B, F

6, 7

46

Lindbergh Drive from Peacthree Road to City Limits

1



2004

0

Gen. Fund/ Federal

DPW

n. i.

B,F

6,7

47

Loridans Drive from Wieuca Road to Stoval Boulevard



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

B

7

48

Lynhurst Drive from MLK Jr. Drive to Cascade Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

I

10,11

49

Marietta Blvd from Chattahoochee River to Howell Mill Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

D

9

50

MLK Jr. Drive from Hightower MARTA station to City Limits


5


2019

9

Gen. Fund/ Federal

DPW

n. i.

H,I

10

51

MLK Jr. Drive from Hightower MARTA station to Hill Street



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

I,J,K

2,3,5,10

52

Miscellaneous Bike Route Connections

1

5

15

2019

0

Gen. Fund/ Federal

DPW

n. i.

all

all

53

Morningside Drive from Wildwood to Lanier Blvd



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

F

6

54

Mount Gilead Road from Headland Drive to Fairburn Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

P,R

11

55

Mount Paran Road from Paces Ferry to Chastain Park



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

A

8

56

Niskey Lake Road from City Limits to Butner Road



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

P

11

57

North Avenue from Bedford Place to Candler Park



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

E,F

2,6

58

North Avenue, from Hightower Rd. to J. P. Brawley Dr.



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

J,K

3

59

North Highland from Virginia Ave to McDonough Blvd

1



2004

17

Gen. Fund/ Federal

DPW

n. i.

N,O,W

1,2,5,6

60

Northside Drive from Simpson Street to RDA Boulevard



15

2019

0

Gen. Fund/ Federal

DPW

n. i.

L,M,V

3,4

61

Northside Pkwy from Chattahoochee River to Moores Mill Rd.


5


2019

11

Gen. Fund/ Federal


DPW

n. i.

A,C

8

62

Oakdale Road/ Whitefoord Avenue from City Limits to Eastside Trolley Trail



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

N,O

5,6

63

Old Ivy Rd from Chastain Park to Peachtree Rd


5


2019

7

Gen. Fund/ Federal


DPW

n. i.

B

7,8

64

Oliver Road from Butner Road to Continental Colony Parkway



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

P,R

11

65

Ormewood Avenue from Boulevard to Flat Shoals Avenue


5


2009

0

Gen. Fund/ Federal


DPW

n. i.



66

Paces Ferry Road from Chattahoochee River to Lenox Road



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

A,B

7,8

67

Parkway Drive from Highland Avenue to Tenth Street



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

F

6

68

Peachtree Battle Ave. from Peachtree Rd. to Moores Mill Rd.



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

C

8

69

Peachtree Road from Wesley Road to City Limits



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

B

7

70

Peachtree Street from Whitehall St to Wesley Rd


5


2009

22

Gen. Fund/ Federal


DPW

n. i.

B,E,M

2,6,7,8

71

Perry Boulevard from Hollywood Road to Howell Mill Road



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

G,K

8,9

72

Piedmont, Juniper & Courtland fr 14th to Ridge


5


2009

11

Gen. Fund/ Federal


DPW

n. i.

E,M,V

2,6

73

Ralph D. Abernathy Boulevard/Georgia Ave. from Cascade Rd. to Grant Park

1



2004

20

Gen. Fund/ Federal


DPW

n. i.

T, V, W

1, 2, 4

74

Ralph McGill Blvd from J. P. Brawley to Freedom Parkway



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

M,N

2

75

Ridgewood Road from Moores Mill Road to Paces Ferry Road



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

A

8

76

S. Ponce de Leon fr Freedom Park Trail to City Limits


5


2009

4

Gen. Fund/ Federal


DPW

n. i.

N

6

77

Simpson Road from James P. Brawley Drive to Jackson Pkwy

1



2004

6

Gen. Fund/ Federal


DPW

n. i.

J, K, L

3

78

Southside Park-Crown Road via Browns Mill Road, Gilbert Road and Southside Industrial Parkway



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

Z

12

79

St Charles Place from Virginia Avenue to City Limits



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

F

6

80

Techwood Dr fr 10th St to Marietta St

1



2004

4

Gen. Fund/ Federal


DPW

n. i.

L

2

81

Tenth fr Howell Mill to City Limits

1



2004

12

Gen. Fund/ Federal

DPW

n. i.

E

2,6,8

82

West Lake Avenue from North Avenue to Hampton Trail



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

I,J,T

3,10

83

West Wesley Road fr Moores Mill to Lenox Rd

1



2004

16

Gen. Fund/ Federal


DPW

n. i.

A,B,C

7,8

84

Westview Drive from Westview Cemetery to RDA Boulevard



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

M,N,O,T,W

2,4,5

85

Wyman Street from Boulevard to City Limits



15

2019

0

Gen. Fund/ Federal


DPW

n. i.

W

5




New, Completed, and Deleted Programs and Projects

Project List 9-13: 2004 CDP Transportation New Programs and Projects – Bicycle Faciltiies

Transportation Bicycle Facilities

Description

Initiation Year

Completion Year

COST

x 1,000

Funding Source

Responsible Party

CIP #

NPU

CD

1

D.L. Hollowell Parkway to City Limits


5


2009

0

GDOT/ Federal



n. i.

G, J, K, L

3, 9